Which cure time is essential before setting tile on Portland cement mortar bed?

Prepare for Nevada's C-20 ANSI Tiling Test. Study flashcards and tackle multiple choice questions, complete with hints and explanations. Ace your exam today!

The essential cure time before setting tile on a Portland cement mortar bed is 96 hours. This duration allows the Portland cement mortar to achieve sufficient strength and moisture levels necessary for effective tile adhesion. During this curing phase, the mortar undergoes hydration, which is crucial for developing the desired compressive strength and stability.

Setting tiles on a freshly laid mortar bed too soon can lead to various issues, such as inadequate bonding, eventual cracking, or even complete failure of the tile installation. The 96-hour period is widely accepted in industry standards to ensure that the bed has cured properly, allowing it to support the weight and rigidity required once the tile is applied. In addition, this timeframe helps prevent moisture from being trapped under the tiles, which can lead to mold growth and tile disbondment.

In summary, allowing a proper cure time of 96 hours before setting tile guarantees a stronger and more durable installation, aligning with best practices within the tiling and construction industry.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy